Inline quality control inspection on the production line at a Guangzhou garment factory

Production takes 6-10 weeks. Somehow your order took 16. Neither number was a lie, they were measuring different things.

What the 6-10 weeks actually covers

Cutting, sewing, finishing, inspection. That's it. Fabric isn't in there. Sampling isn't in there. Shipping definitely isn't.

Add them up and the real timeline looks like this:

Realistically five to six months from first email to landed goods, if you're sampling properly.

Where it actually slips

In our experience, in this order:

Fabric confirmation. The biggest single variable. A factory that books the production line before the mill confirms your fabric has committed to a date it doesn't control. When the mill slips, everything slips. We confirm the date only after the mill does, which means we occasionally quote a later date than a competitor. That date holds.

Sample approval delays on your side. Not a criticism, just arithmetic. A week to review a sample is a week off the back end. Two rounds of that and you've lost a fortnight.

Scope changes mid-production. Changing a trim after cutting starts is not a small change. It's a re-order and a re-schedule.

Re-dyes. If a lab dip fails, that's another 1-2 weeks. It happens. Plan for one.

How to lock it

Get the date in writing, with the dependencies named. Not "delivery by October" but "production starts when fabric is confirmed and inspected; 8 weeks from that date."

Ask what happens if fabric is late. A factory with a real answer has done this before.

Then track it. We give live order tracking, not because it's a feature but because "where's my order" emails are a symptom of nobody knowing.

Sea or air

Air is 5-8 days and costs several times more. Sea is 18-25 days. On 30 pieces, air is usually worth it. On 500, the maths flips.

Factor duties and customs into both, the shipping quote isn't the landed cost, and this is where a lot of first-time importers get surprised.