
Production takes 6-10 weeks. Somehow your order took 16. Neither number was a lie, they were measuring different things.
What the 6-10 weeks actually covers
Cutting, sewing, finishing, inspection. That's it. Fabric isn't in there. Sampling isn't in there. Shipping definitely isn't.
Add them up and the real timeline looks like this:
- Tech pack and quoting, a few days to a week, longer if the spec is thin
- Mock-up rounds, 14-21 days each, and most brands need 2-3
- Final sample, 28-42 days in the correct fabric
- Fabric sourcing, 2-4 weeks, starting when the mill confirms
- Production, 6-10 weeks
- QC and packing, 3-5 days
- Shipping, 5-8 days by air, 18-25 by sea
Realistically five to six months from first email to landed goods, if you're sampling properly.
Where it actually slips
In our experience, in this order:
Fabric confirmation. The biggest single variable. A factory that books the production line before the mill confirms your fabric has committed to a date it doesn't control. When the mill slips, everything slips. We confirm the date only after the mill does, which means we occasionally quote a later date than a competitor. That date holds.
Sample approval delays on your side. Not a criticism, just arithmetic. A week to review a sample is a week off the back end. Two rounds of that and you've lost a fortnight.
Scope changes mid-production. Changing a trim after cutting starts is not a small change. It's a re-order and a re-schedule.
Re-dyes. If a lab dip fails, that's another 1-2 weeks. It happens. Plan for one.
How to lock it
Get the date in writing, with the dependencies named. Not "delivery by October" but "production starts when fabric is confirmed and inspected; 8 weeks from that date."
Ask what happens if fabric is late. A factory with a real answer has done this before.
Then track it. We give live order tracking, not because it's a feature but because "where's my order" emails are a symptom of nobody knowing.
Sea or air
Air is 5-8 days and costs several times more. Sea is 18-25 days. On 30 pieces, air is usually worth it. On 500, the maths flips.
Factor duties and customs into both, the shipping quote isn't the landed cost, and this is where a lot of first-time importers get surprised.
Go deeper: 5 production mistakes: booking the line before fabric confirms
Questions we get about this
How long does clothing production take from start to finish?
Five to six months from first email to landed goods if you sample properly: tech pack, 2-3 mock-up rounds at 14-21 days each, final sample 28-42 days, fabric 2-4 weeks, production 6-10 weeks, then shipping.
Why did my factory miss the delivery date?
Usually because the line was booked before the mill confirmed fabric. A factory that commits before fabric is confirmed doesn't control the date.
Should I ship by air or sea?
Air is 5-8 days and costs several times more. On 30 pieces air usually wins; on 500 the maths flips to sea at 18-25 days. Factor duties into both.



